Aug. 27, 2019

MONDAY:8-12-2019
Installing the TPO on the low roof building A
Terminating wire to the main transformer. Grouting the stone around building A
Installing densglass around building B
Framing and installing densglass on level 1 building A
Water proofing building B
& installing window frames and glass on level 2


TUESDAY:8-13-2019
Waterproofing building B
Installing densglass on level 1 building A
Poured the northside sidewalk near the bank
Installing window frames & glass on level 2
Terminating wire to the main transformer. Grouting the stone around building A


WEDNESDAY:8-14-2019
Hanging densglass building B & Interior framing in building A level 1, Forming and installing rebar on the south stairs
Installing window frames and glass building A level 2
Installing the TPO on the roof of building B
Installing rigid insulation around building B
Clearing the brush from the north tree line.


THURSDAY:8-15-2019
Clearing the brush from the north tree line & Grouting the stone around building A
Interior framing level 1 & hanging sheet rock in building A
Installing the TPO on the roof of building B
Installing rigid insulation around building B, Installing stone on the east side of building A
Installing window frames on level 2 building A Forming and installing rebar on the south stairs


FRIDAY 8-16-2019
Terminating wire to the main transformer. Grouting the stone around building A
Hanging sheet rock on level 2 building A
Installing the TPO on the roof of building B
Installing rigid insulation around building B building
Installing sprinkler pipes in building B Installing window frames on level 2 building A